COMMODITY/SERVICE SOUGHT: Pioneer Ditch Piping Installation Services
SOLICITATION NO.: WC1-058-2023-01
PROPOSAL DUE DATE AND TIME: April 22, 2026 – 5:00 p.m. Arizona Local Time
LOCATION: Email

The Verde NRCD (“district”) is seeking sealed bids (“Bids”) from qualified Vendors (“Vendors”) capable of providing the following goods and/or services:

Pioneer Ditch Piping Installation Services

Schedule of Events:

Questions Due Date:April 10, 2026 – 5:00 p.m.
Submittal Due Date: April 22, 2026 – 5:00 p.m.
Submittal Location: Via email to alicia@aliciapeckconsulting.com

The work includes procurement and installation of approximately:

  • 3300 ft of 24″ DR32.5 HDPE pipeline
  •  ~20 ft of 30″ DR32.5 HDPE pipeline, ≤500 ft total of 15″ and 18″ HDPE pipelines
  • Concrete diversion and inlet structures
  • Multiple check and turnout structures
  • Alfalfa valve assemblies and air vents
  • Flow meter vault with ultrasonic flow meter system
  • Associated grading, compaction, trenching, backfill, and surface restoration
  • Fusion welding of pipes using a fusion machine provided by the Vendor
  • Installation of turnouts and structures in accordance with the detailed engineering design
  • Backfilling of the pipeline that will be done using source fill and in accordance with engineering specifications, ensuring structural integrity and optimal functionality
  • Ensuring strict compliance with Occupational Safety and Health Administration (OSHA) guidelines for safety during all phases of construction is imperative